Site icon IRCTC NEWS

pre monsoon preparations works by Western railway

pre monsoon preparations works by Western railway

प्रेस विज्ञप्ति के अनुसार स्थानीय रेलगाड़ियों के पहियों को चलाने और आने वाले मॉनसून के दौरान निर्बाध सेवाओं को सुनिश्चित करने के लिए, पूर्व मानसून की तैयारी के काम पूरे पश्चिमी रेलवे पर चल रहे हैं। इन तैयारियों में कल्वर की सफाई, साइड नालियों को हटाने, उच्च शक्ति पंपों की स्थापना, बुनियादी ढांचे के विशेष रखरखाव इत्यादि शामिल हैं। ये कार्य 1, जून 2018 तक पहले चरण में पूरा किए जाएंगे।

As per Press Released  In order to keep the wheels of local trains running and to ensure uninterrupted services during the ensuing monsoon, pre monsoon preparations works are undergoing o­n Western Railway in full swing. These preparations include cleaning of culverts, desilting of side drains, installations of high power pumps, special maintenance of infrastructure etc. These works will be completed by 1st, June 2018 in the first phase.

बीएमसी के साथ समन्वय: पूर्व-सफाई रेलवे और बीएमसी अधिकारियों के संयुक्त निरीक्षण किए गए हैं। अब, कल्वर की सफाई के बाद, संयुक्त निरीक्षण के बाद संयुक्त निरीक्षण की योजना बनाई गई है। इसमें बीएमसी द्वारा उन स्थानों पर पंप के प्रावधान भी शामिल हैं जहां जल निकासी में अवरोध होने की संभावना है। आपातकाल के दौरान तेजी से संचार के लिए एमसीजीएम आपदा नियंत्रण और पश्चिमी रेलवे यातायात नियंत्रण के बीच एक हॉटलाइन स्थापित की गई है।

Analysis of Rainfall and Flood prone areas:

पश्चिमी रेलवे ने अपने खंड पर बाढ़ प्रवण क्षेत्रों की पहचान की है। इस विश्लेषण के आधार पर, कुछ हिस्सों पर अधिक ध्यान दिया जाएगा जो बाढ़ प्रवण हो सकते हैं जैसे ग्रांट रोड, एलफिंस्टन रोड, दादर, मतुंगा आरडी-महिम यार्ड, बांद्रा-खार, अंधेरी-जोगेश्वरी और नालसोपारा-विरार खंड ।

पश्चिमी रेलवे भी समय सारणी के साथ आया है जो 1 जून, 2018 से 30 सितंबर, 2018 तक मानसून 2018 के दौरान 4.0 मीटर से अधिक की उच्च ज्वार की तिथियां दिखा रहा है। यह आवश्यक होने पर आवश्यक सावधानी बरतने में मदद करेगा।

Western Railway has also come up with the time table showing the dates of high tides of more than 4.0 meters during monsoon 2018 from 1st June, 2018 to 30th Sept, 2018. This will help in taking necessary precautions when required most.

 

Special Pre-monsoon Action (विशेष प्री-मॉनसून एक्शन):

>First round of desilting in all 40 Culvert has been completed, for balance 3, the target date is 25/05/2018. Subsequent round of desilting will be completed after conducting Joint inspection of first round. Remaining major culverts will be cleaned by the BMC which include Mithi river, Dharavi Nallah, Poisar nallah, etc. Joint inspection are also being carried out by railway and MCGM officials.

>Lifting of tracks in low lying areas has already been completed in Mahim Yard o­n Harbour lines and between Bandra-Khar Down slow line where water logging had been observed.

>Lowering of cess along side of tracks is under progress.

>WR has installed about 100 high power pumps at vulnerable low lying locations such as Marine Lines, Mumbai Central, Dadar, Matunga Road, Mahim, Bandra, Andheri, Borivali, Nalasopara, Virar etc.

>WR has also undertaken the work of desilting of side drains. This work will be completed before the o­nset of monsoon. After reviewing the position, this work may again be undertaken in July and August, 2018 as per requirement.

>In order to ensure smooth running of trains during monsoon, special attention is also being given to the maintenance of OHE. This includes cleaning of insulators, checking of protective screens o­n FOB/ROB, protection of contact and catenary wires and earthing.

>Cutting & trimming of vulnerable trees in the vicinity of track will also be done.

>WR has also taken up the monsoon related maintenance work of its EMU suburban rakes which include detection & plugging of possible leakages in EMU coaches and its electrical equipments, smooth movements of windows & doors etc. Work of cleaning of roof of coaches and insulators has also been taken up in hand.

pre monsoon preparations works by Western railway
Exit mobile version